Project Updates

2017 Bond Project Updates

Projects in the 2017 Bond Program are divided into four primary subcategories:

Updates for projects completed or in progress in these particular areas, as well as a list of upcoming projects, can be found on the links to the left identifying each subcategory.

Project Updates by Program Manager John Haugen

Dec. 4, 2017 Bond Board Update

Nov. 29, 2017 PTO President's Update

Nov. 28, 2017 CMS PTO Update

Nov. 13, 2017 Bond Board Update

Sept. 11, 2017 Bond Board Update

Back to Top


Campus By Campus Project List

Lifecycle projects are those projects that involve replacement or a refresh like paint, carpet, roofs, HVAC systems, tile, wall coverings, etc.

Elementary Schools

Carroll Elementary - $13,500,000

(Upgrades & Capacity $3,500,000 / Lifecycle $10,000,000)

Projected Substantial Completion Date - Spring 2019

  • 6-Classroom Addition
  • New Freezer / Cooler Area for the Kitchen
  • Upgrades and Renovations to Classrooms and Administration Areas
  • Additional and Renovate Restrooms
  • New Stage and Equipment
  • New 2x2 Ceilings (what are 2X2 acoustical tile ceilings?)
  • Additional Windows for Existing Classrooms
  • Redesign the schools within the schools
  • New Flooring as required
  • Resurface Interior Walls of corridors, classrooms, etc…
  • Electrical Upgrades
  • Improvements to the Exterior Skin of the Building, Roof, Structure, etc…
  • New Playground Surface
  • Site work Improvements
  • Technology Upgrades
  • Safety and Security
  • Furniture, Fixtures & Equipment (FF&E)

Johnson Elementary - $13,500,000

(Upgrades & Capacity $4,500,000 / Lifecycle $9,000,000)

Projected Substantial Completion Date - Spring 2019

  • 6-Classroom Addition
  • New Gymnasium
  • Renovate Restrooms
  • Renovate the Auditorium
  • Additional and Renovate Custodial Closets
  • New 2x2 Ceilings
  • Additional Windows for Existing Classrooms
  • Redesign the schools within the school (building divided into specific grade-level wings)
  • New Flooring as required
  • Resurface Interior Walls of corridors, classrooms, etc…
  • Electrical Upgrades
  • Improvements to the Exterior Skin of the Building, Brick Work, etc…
  • Site work Improvements
  • Technology Upgrades
  • Safety and Security
  • Furniture, Fixtures & Equipment (FF&E)

Rockenbaugh Elementary - $10,000,000

(Upgrades & Capacity $2,000,000 / Lifecycle $8,000,000)

Projected Substantial Completion Date - Fall 2019

  • Addition of a New Administration Area at the Front of the building
  • Renovate Old Administration area into 6 Classrooms / Breakout Spaces
  • Renovate Restrooms
  • New 2x2 Ceilings
  • New Flooring as required
  • Resurface Interior Walls of corridors, classrooms, etc…
  • Electrical Upgrades
  • Fire Alarm Upgrades
  • Improvements to the Exterior Skin of the Building, Doors, Roof, etc…
  • New Playground Surface
  • New Canopy Systems
  • Site work Improvements
  • Technology Upgrades
  • Safety and Security
  • Furniture, Fixtures & Equipment (FF&E)

Old Union Elementary - $10,000,000

(Upgrades & Capacity $2,000,000 / Lifecycle $8,000,000)

Projected Substantial Completion Date - Spring 2019

  • Addition of 6 New Classrooms with the Master plan 10 more Classrooms
  • Addition of a New Administration Area at the Front of the building
  • Renovate existing Administration Area into 4 New Classrooms
  • Upgrades to Classrooms
  • Renovate Restrooms
  • New 2x2 Ceilings
  • New Flooring as Required
  • Resurface interior Walls of corridors, classrooms, etc…
  • Electrical Upgrades
  • Fire Alarm Upgrades
  • Improvements to the Exterior Skin of the Building, Doors, Roof, etc…
  • New Playground Surface
  • New Canopy Systems
  • Site Work Improvements
  • New Sound System Equipment
  • Technology Upgrades
  • Safety and Security
  • Furniture, Fixtures & Equipment (FF&E)

Walnut Grove Elementary (Upgrades & Capacity) - $2,000,000

Projected Substantial Completion Date - Fall 2019

  • 4-Classroom / Computer Lab Addition
  • Upgrades to Classrooms
  • Renovations to Administration Area
  • Build a Storage area within the Service Yard
  • Site Work Improvements, Additional Parking, Sidewalks, Fencing, etc…
  • Technology Upgrades
  • Safety and Security
  • Furniture, Fixtures & Equipment (FF&E)

Intermediate Schools

Durham Intermediate - $6,000,000

(Upgrades $1,000,000 / Lifecycle $5,000,000)

Projected Substantial Completion Date - Fall 2019

  • Upgrade and Renovate Science Labs
  • Renovate Restrooms
  • Cafeteria / Stage Improvements
  • Miscellaneous Interior Renovations
  • New 2x2 Ceilings
  • New Flooring as required
  • Resurface Interior Walls of corridors, classrooms, etc…
  • New Interior Signage
  • Electrical Upgrades
  • HVAC Upgrades
  • Fire Door Upgrades
  • Improvements to the Exterior Skin of the Building, Doors, Roof, etc…
  • Site Work Improvements
  • Technology Upgrades
  • Safety and Security
  • Furniture, Fixtures & Equipment (FF&E)

Eubanks Intermediate - $8,000,000

(Upgrades & Capacity $2,000,000 / Lifecycle $6,000,000)

Projected Substantial Completion Date - Fall 2019

  • New Addition to Band / Choir Halls
  • Miscellaneous Interior Renovations
  • New 2x2 Ceilings
  • Resurface Interior Walls of corridors, classrooms, etc…
  • New Flooring as required
  • HVAC Upgrades
  • New Canopy Systems
  • Site Work Improvements
  • Technology Upgrades
  • Safety and Security
  • Furniture, Fixtures & Equipment (FF&E)

Middle Schools

Dawson Middle School - $6,000,000

(Upgrades $500,000 / Lifecycle $5,500,000)

Projected Substantial Completion Date - Fall 2020

  • Renovate Restrooms
  • Renovations to the Gymnasium
  • Band/Choir Renovations and Practice Rooms
  • New 2x2 Ceilings
  • Resurface Interior Walls of corridors, classrooms, etc…
  • New Flooring as required
  • HVAC Upgrades
  • Improvements to the Exterior Skin of the Building, Doors, Roofs, etc…
  • New Canopy Systems
  • New Track with additional drainage system
  • Turf Field
  • Site Work Improvements
  • Technology Upgrades
  • Safety and Security
  • Furniture, Fixtures & Equipment (FF&E)

Carroll Middle School - $3,000,000

(Upgrades $2,500,000 / Lifecycle $500,000)

Projected Substantial Completion Date - Spring 2019

  • Resurface Interior Walls of corridors, classrooms, etc…
  • Miscellaneous Interior Renovations
  • Architectural Interior Acoustical Work
  • Storage Facility
  • New Track and Field Renovations
  • Turf Field
  • Site Work Improvements
  • Technology Upgrades
  • Safety and Security
  • Furniture, Fixtures & Equipment (FF&E)

High Schools

Carroll High School - $14,000,000

(Upgrades $3,000,000 / Lifecycle $11,000,000)

Projected Substantial Completion Date - Fall 2020

  • Renovate Existing Band Hall Facilities STEM Program
  • Renovate Science Labs
  • Renovate Library
  • Renovate Girls Locker Rooms for Better Security
  • New Locker Room for Girls Wrestling
  • Renovate Restrooms
  • New 2x2 Ceilings
  • New Flooring as required
  • Resurface Interior Walls of corridors, classrooms, etc…
  • Fire Door Upgrades
  • Improvements to the Exterior Skin of the Building, Brick, Roof, etc…
  • New Canopy Systems
  • Upgrades to Baseball and Softball Facilities
  • Upgrades to Football Field and Track Facilities
  • Turf Field
  • Site work Improvements
  • Technology Upgrades
  • Safety and Security
  • Furniture, Fixtures & Equipment (FF&E)

Carroll Senior High - $27,000,000

(Upgrades $8,000,000 / Lifecycle $19,000,000)

Projected Substantial Completion Date - Fall 2020

  • Renovate the Existing Auditorium and Support Spaces
  • Renovate and Repurpose Existing Classrooms
  • Renovate Student Activity Center and Food Court / Kitchen
  • Renovate Restrooms
  • Resurface Interior Walls of corridors, classrooms, etc…
  • New 2x2 Ceilings
  • HVAC Upgrades
  • Improvements to the Exterior Skin of the Building, Doors, Roofs, etc…
  • New Exterior Skin of the Indoor Workout Facility
  • Miscellaneous Renovation and Upgrades in Field House / Indoor
  • New Canopy Systems
  • Upgrades to Baseball and Softball Facilities
  • Upgrades to Football Field and Track Facilities
  • 4 Turf Fields
  • Site Work Improvements
  • Technology Upgrades
  • Safety and Security
  • Furniture, Fixtures & Equipment (FF&E)

Other Projects

New Music Center - $24,000,000

Projected Substantial Completion Date - Fall 2019

  • Auditorium at Carroll Sr High to seat 700
  • Band Halls
  • Choir Halls
  • All related support elements

Aquatics Center - $5,000,000

(Upgrades $500,000 / Lifecycle $4,500,000)

Projected Substantial Completion Date - Fall 2019

  • Major Repairs to the Pool
  • Renovation and Upgrades to Pool Area and Equipment
  • Renovate and Upgrade of Pool Mechanical Room and Equipment
  • Renovate Locker Rooms as required
  • Renovate Concession Area
  • Lighting Upgrades
  • Electrical Upgrades
  • Technology Upgrades
  • Safety and Security
  • Furniture, Fixtures & Equipment (FF&E)

Dragon Stadium - $4,000,000

(Upgrades $250,000 / Lifecycle $3,750,000)

Projected Substantial Completion Date - Fall 2019

  • Replace Seating on the Home side as required
  • Renovate Restrooms as required
  • Resurface Finishes as required
  • Turf Replacement
  • Press Box Upgrades
  • New Graphics as required
  • Lighting Upgrades
  • Electrical Upgrades
  • Fire Alarm Upgrades
  • Upgrade and Renovate Parking as required
  • Upgrade and Replace Fencing and Gates as required
  • Site Work Improvements
  • Technology Upgrades
  • Safety and Security
  • Furniture, Fixtures & Equipment (FF&E)

Transportation Facility - $1,000,000

(Upgrades $300,000 / Lifecycle $700,000)

Projected Substantial Completion Date - Fall 2019

  • Miscellaneous Renovations to allow for better use of the Facility
  • Renovate Restrooms as required
  • Resurface Finishes as required
  • Mechanical Upgrades
  • Lighting Upgrades
  • Electrical Upgrades
  • Alarm Upgrades
  • Upgrade and Renovate Parking as required
  • Upgrade and Replace Fencing and Gates as required
  • Site Work Improvements
  • Technology Upgrades
  • Safety and Security
  • Furniture, Fixtures & Equipment (FF&E)

Carroll Administration - $6,000,000

(Upgrades $500,000 / Lifecycle $5,500,000)

Projected Substantial Completion Date - Fall 2020

  • Miscellaneous Interior Renovations and Upgrades
  • Renovate Restrooms
  • New 2x2 Ceilings
  • Architectural Interior Acoustical Work
  • Electrical Upgrades
  • Plumbing Upgrades
  • HVAC Upgrades
  • Improvements to the Exterior Skin of the Building, Roof, etc…
  • Site Work Improvements
  • Technology Upgrades
  • Safety and Security
  • Furniture, Fixtures & Equipment (FF&E)

District Wide Needs - $1,000,000

  • 21st Century Learning Requirements
  • Artificial Turf
  • Irrigation Wells
  • HVAC / Geo-Thermal / Other
  • LED Lighting

Technology - $45,000,000

  • Infrastructure
  • Student Devices
  • Teacher Presentation Resources

Transportation - $7,500,000

  • Buses - regular route buses, special needs buses, activity buses
  • Other Maintenance Vehicles

Band - $1,500,000

Instruments for all bands from intermediate campuses through senior high


TOTAL $208,000,000

Questions about ongoing work of the 2017 Bond Program may be directed to Program Manager John Haugen - john.haugen@southlakecarroll.edu.

Back to top